Perfect Strip Out & Demolition completed strip-out and demolition works at an aged care facility located in Beecroft.
The scope of work for this project involved:
- Strip out kitchens;
- Demolition of laundries;
- Strip out bathrooms;
- Disassemble cold rooms;
- Removal of plasterboard ceiling (approximately 3,245m2);
- Demolition of plasterboard lining on brick walls;
- Disassemble vinyl floor finish (approximately 2870m2);
- Removal of doors, joinery, and cabinets;
- Demolition of reception desks;
- Removal and disposal of loose furniture and mattresses;
- Disassemble air conditioning ducting and other existing ducting;
- Demolition and removal of the single and double skin brick walls, and concrete slabs;
- Disassemble and remove concrete pavings, slabs, plinths and steps, and bitumen footpath;
- Demolition of the existing section of the heritage house including the timber roof structure, windows, brick walls and sandstone and nearby shed;
- Demolition and removal safely of the metal roof and roof structure;
- Rubbish removal from the job site and disposal, recycling or reusing them according to EPA.
1.8T excavator for materials handling, hook trucks, skip bins & bogies for material loadout were used during this project. Our team utilised electrical tools such as grinders, demolition and ring saws, jackhammers and hand tools.






Perfect Group acknowledges the Aboriginal and Torres Strait Isander people as Traditional Custodians of the country on which we live and work. We pay our respects to the Traditional Custodians and Elders past, present and future, and honour their connection to the land and ongoing contribution to society.