Perfect Contracting completed demolition and construction works for Blue Mountains Route Clearance – Continuum Alliance (CPB, Lend Lease, Transport for NSW joint venture).
The scope of work for this project involved:
- Station cutbacks required trimming back sections of the existing platform to clear the new, wider trains. Over two kilometres of the platform were trimmed;
- Station buildout required installing precast concrete panels to ‘build out’ sections of the platform to bridge any gaps deemed unsafe by TfNSW. Almost eight hundred metres of precast panels were installed.
Hundreds of workers, fourteen subcontractors, three principal contractors, one joint venture and eighteen months of meticulous planning came down to just eight possession weekends to finish all work.
All on heritage listed train stations, all on time and with zero LTI’s or remaining defects.






Perfect Group acknowledges the Aboriginal and Torres Strait Isander people as Traditional Custodians of the country on which we live and work. We pay our respects to the Traditional Custodians and Elders past, present and future, and honour their connection to the land and ongoing contribution to society.