Perfect Strip Out & Demolition completed the strip-out of two office levels in North Ryde.
The scope of work for this project involved:
- Removal of existing carpet;
- Removal of carpet tiles;
- Strip-out of male and female toilets;
- Removal of all gyprock partitions;
- Removal of doors, toilet fixtures & partitions;
- Disassemble workstations;
- Demolition of the reception desk (3.5m x 1m) while keeping the existing flooring and floor matt intact;
- Segregation and removal of all waste from the site by Tipper Trucks;
- Recycling 100% of the waste removed from sites.
Overall, over 44 tons of waste were removed, including 8 t of steel and 36 t of general light mixed waste.






Perfect Group acknowledges the Aboriginal and Torres Strait Isander people as Traditional Custodians of the country on which we live and work. We pay our respects to the Traditional Custodians and Elders past, present and future, and honour their connection to the land and ongoing contribution to society.