PROJECT DETAILS

2019

Principal Contractor

Central Coast Metal Protectives

Sector

State

NSW

Perfect Concrete Care was engaged to undertake floor grinding & epoxy removal on the Taronga Zoo wharf.

The scope of work for this project involved:

Floor grinding by 2 concrete care operators;

Removal of existing epoxy slowly by grinding off the membrane with aggressive diamonds on the wharf using our Floorex Satellite rotary grinder with Tyrolit dust extractor systems;

Application of zip walls and plastic protection all around the whole wharf to ensure no dust or waste would get into the waterways

The project happened in 2 stages as one side of the wharf was closed for each stage of the job so the ferry could still operate.

Related projects

Perfect Group, your trusted delivery partner

With a track record of successfully delivering complex projects on time and within budget. Our team of experienced professionals and a commitment to using the latest equipment and technologies, The Perfect Group provides a comprehensive range of services that are tailored to meet the specific needs of each client. With a focus on delivering results and building long-term relationships, The Perfect Group is your trusted partner for all your project delivery needs.