Perfect Concrete Care completed specialised wall sawing for our client Continuum Alliance at several stations in the Blue Mountains area. The works covered stations such as Leura Station, Lawson Station, Blackheath Station, Medlow Bath Station, Lithgow Station and Katoomba Station.

The scope of work for this project involved:

Cutbacks of the platform with our Tyrolit WSE1217 Wall Saw

Vertical wall sawing on the existing coping edge

Horizontal wall sawing on the existing coping edge

Marking out the area with Hilti Laser Levels to make accurate cuts

Installation of the track for the wall saw on the coping edge

Installation of the wall saw rail onto the opposite side to make the horizontal cuts.

The goal of the work was to install precast panels that extend the platform. The team carried out all work without incident. New precast panels could be installed before the station was open again on Monday morning.

Our client was very impressed with the speed and efficiency of our team members and the quality of the work carried out.

Related projects

Perfect Group, your trusted delivery partner

With a track record of successfully delivering complex projects on time and within budget. Our team of experienced professionals and a commitment to using the latest equipment and technologies, The Perfect Group provides a comprehensive range of services that are tailored to meet the specific needs of each client. With a focus on delivering results and building long-term relationships, The Perfect Group is your trusted partner for all your project delivery needs.